Latest
Status
The Team are now back in Scotland and hard at work following a recent
trip to Hilo to become acquanted with the UKIRT team and gain clarifcation
on Interface issues.
Click here
to take you to the latest WFCAM designs and some pictures from their trip.
WFCAM
Conceptual Design Review
The conceptual WFCAM design
was successfully presented in detail to an external CoDR panel and other
attendees over one and a half days on August 31 & September 1 1999.
The external panel consisted of Ray Sharples (chair-Durham), Ron Probst
(NOAO), Ian Parry (Cambridge) and Andy Adamson (JAC). Other attendees
from JAC, ATC and SUBARU were also present. Final remarks from the panel
report were as follows,
"At
this conceptual review point, the project appears to support exciting
science opportunities, in a manner appropriate for a 4-m class telescope
in the era of 8-m competition. The concept is a novel but sound approach
given the design constraints (no new top end, tip-tilt secondary of conservative
size). It appears technically feasible, with a sound technical and management
approach to final design and execution. Some costs have large error bars,
as expected at this point in the project cycle. Being schedule-driven
and cost-constrained, a generous contingency is prudent. Bringing in an
8-m partner in a manner that supports the ultimate science goals is an
excellent idea."
Latest
Status from Director's Review
The latest Director's Review
of the Project took place in February 2001. It described WFCAM as follows:
The Importance of WFCAM
Primary:
- Most powerful
wide-field IR imager in the world
- 300 x survey speed of
UFTI
- First deep near-IR survey
of large areas of sky
- Access to universe beyond
z=1
- High-z clusters
- Oscured quasars and AGN
- Brown dwarf studies
- Low-mass limits to star
formation Large IR catalogues and atlases will give UK astronomers
advantage in 8m access
Secondary:
- New optical design concept
- Forward cassegrain
- Large cold M3 + 2 correctors
- VISTA synergy detector
- Technology observing and
data reduction strategies
- Catalogue and atlas production
Milestones
Project start |
October 1998 |
CoDR |
September 1999 |
PDR |
May 2001 |
CDR |
October 2001 |
Acceptance Test |
July 2003 |
Delivery |
August 2003 |
|
|
Recent
Accomplishments
- SUBARU funded detectors
on order
- Internal Requirements
Review successfully completed
- Prototype array PCB
designed, procured and assembled
- Provisional Mechanical
Layout completed
- Test cryostat re-furbished
and set up for array characterisation tests
- Initial optical tolerance
and flexure analysis completed
Near
Term Goals
Previous Review:
- Select detector controller
unit (November 2000)
- Characterise 2048 x 2048
array (December 2000)
- Ensure SUBARU funded detectors
are ordered (September 2000)
- CDR’s complete by mid
2001
- Revised and robust project
plan in place (September 2000)
This Review:
- Selection of detector
controller (April 01)
- Characterise 2k X 2k array
(May 01)
- PDR (May 01)CDR (Oct/Nov
01)
- Place order for long lead
time optics (May / June 01)
- Hexapod order place (June
01 )
|