1. Safety
1.1 Hazards
The Quantumcooler Liquefier/Reliquefier produces liquid helium.
Consequently, like all equipment using cryogens, certain hazards
are present.
The Quantumcooler System is equipped with a number safety relief
valves and other safety features which protect the system. These
must not be tampered with.
Improper use of this liquefier could pose a hazard to
personnel and property.
The potential hazards are catastrophic rupture if unvented vessels,
freezing damage from splashing cryogens and asphyxiation hazard
from high concentrations of helium gas. It is the customers responsibility
to ensure that the installation is monitored so that a cooling water
leak near a compressor would not cause any damage.
Catastrophic rupture can occur if a cryogen is held in a sealed
container while warming. The high pressures generated can burst
the container, resulting in a hazard. All cold vessels including
the vaccum space within the Quantumcooler are equipped with safety
relief valves
|
1.2 Asphyxiation Hazard
No catastrophic ruptures nor asphyxiation hazard conditions
have been reported with Quantum equipment. This section of the manual
is not intended to alarm the user but rather to explain the purpose
of the numerous safety features.
High concentrations of helium gas in a room constitute an asphyxiation
hazard. Although non-poisonous, the gas may reduce the concentration
of oxygen below safe levels. When the helium concentration is extremely
high, then the oxygen in solution in the blood will diffuse out
causing a rapid collapse and possible death.
Every year people die when inhaling helium gas to
try the "squeaky voice trick". A single deep inhalation
of helium gas can be fatal. It is strongly recommended that this
"trick" not be attempted.
In small rooms of confined spaces where there is insufficient
natural ventilation, or where
the volume of helium which could potentially be released exceeds
20% of the room
volume it is recommended that a low oxygen meter with an audible
alarm be permanently
installed at shoulder height in the liquefier room. A placard
advising non-entry in the
event of an alarm should be affixed to the outside of the room.
|
2.0 Principles of Operation
2.1 Principles of Operation
Values given here are for illustration only. Always refer to Section
3.3, Recommended Pressures & Settings for system
adjustment.
The Quantumcooler Liquefier/Reliquefier is a three stage closed-cycle
refrigerator. See section 7.0, Dewar Schematic. The working fluid
in all three stages is an extremely high purity helium gas. The
nominal operating temperatures of the three stages are 70K, 15K
and 4.2K respectively. The first two stages are based on the Gifford-McMahon
(G-M) cycle with helium gas pressure cycled isothermally from 19
bar relative (275 psig) to 5 bar relative (73 psig). The two G-M
stages are linked together and share a single displacer-regenerator.
The upper(large diameter) portion of the displacer is packed with
wire screens and the lower (small diameter) portion is packed with
lead shot to provide sufficient heat capacity for regeneration.
Moving seals force the helium gas through the regeneration media
in the centre of each displacer.
The third stage of refrigeration is a Joule-Thomson (J-T) isenthalpic
expansion stage. Extremely high purity J-T supply gas at 17 bar
relative (250 psig) is cooled to 13K by the previous two G-M stages.
This gas then flows through a counterflow heat exchanger which cools
it to 4.2K and then passes through a J-T orifice producing a cold
mixture of gas and liquid at 1 bar absolute (atmospheric pressure).
The liquid fraction is evaporated in heat STN. #3 to provide cooling
for liquefaction. Gas and liquid leave the station still at 4.2K.
This cold material returns via the counterflow heat exchanger to
the 13K stage, thereby cooling the incoming high pressure gas.
Please refer to Drawing D93000 Appendix E.
|
3 Normal Operation
If the presence of air is suspected in the system, it must be
decontaminated prior to cooldown. See section on decontaminating
helium gas supply.
|
3.1 Start-up
Record all pressures and temperatures on the system log sheet
BEFORE starting and during cooldown. Perform other adjustments as
required by the G-M Manual.
(a) Turn on the cooling water to the water cooled compressors.
The flow through all compressors should be such that when operating
the water outlet temperature is below 45C.
(b) Prior to and during cool-down, monitor and record temperatures
on the attached system logsheet. It is very useful to compare
these temperatures with the standard cool-down curve given the
Test Results section.
(c) The J-T valve is a very fine needle valve and can easily
be damaged by overtightening. Never attempt to fully close this
valve as it may be damaged. Leave the J-T valve at the factory
setting (see section 3.3).
(d) Check that the helium pressure in the J-T / G-M loops
are at the recommended pressure (see section 3.3).
(e) Start the GM compressor and turn on cold head.
(f) Start the JT compressor. When the pressures stabilise,
adjust the regulator on the back of the compressor for a JT
return pressure as shown in the recommended pressure table.
(g) Set JT valve to 2 turns open initial setting.
(h) Check that the cooling water discharge temperature does
not exceed 45C.
(i) Open the JT-"Bypass" valve approximately 3
- 4 turns, and leave open until the 3rd stage temperature approximates
40 degrees Kelvin, at this time the "Bypass" valve
should be adjusted to approximately 2 turns open. When the 3rd
stage temperature reaches approximately 20 degrees Kelvin, then
close the "Bypass" valve to "0" turns open.
Do not attempt to close the Bypass valve passed the "0"
mark on the dial counter knob. Severe damage can result.
THESE
VALVES ARE DELICATE AND CAN BE DAMAGED BY OVERTIGHTENING. INCREASING
NUMBERS INDICATE INCREASED FLOW.
|
3.2 System Shutdown
Switch the JT and GM compressors of and then shut off the cooling
water.
IMPORTANT: Do not disconnect any of the flexible hoses until
after the system has warmed to room temperature. Disconnecting the
self-sealing coupling before allowing a warm-up will result in overpressures
in the cryogenic piping and destruction of the cryocooler. QUANTUM
TECHNOLOGY CORP. IS NOT RESOPONSIBLE FOR ANY DAMAGE CAUSED BY MISUSE.
|
3.3 Recommended Pressures & Settings
|
All Pressures are in PSI
|
WARM
System
OFF
|
COLD
and
Operating
|
See
NOTE
#
|
JT Return |
N/A
|
18'' vacuum
|
1
|
JT Supply |
N/A
|
295
|
2
|
Buffer Tank |
155
|
80-90
|
3
|
JT Valve Setting |
1.00
|
1.00 turns
|
4
|
JT Bypass Valve Setting |
4 cooldown
|
0 closed
|
-
|
GM Inlet Pressure |
N/A
|
40-65
|
-
|
GM Outlet Pressure |
N/A
|
295
|
5
|
Notes:
1) Read JT Return gauge on compressor. Adjusted with JT
valve. The valve at the back of the JT compressor should be
fully closed (fully clockwise).
2) No gauge, set by regulator on buffer tank.
3) Set while warm by initial charge (quantity) of helium
in the system.
4) JT valve useful range is 0 turns open to 4.0 turns open.
When changing the setting, avoid backlash by opening the valve
a full turn before closing the new setpoint desired.
5) Adjusted by regulator on buffer tank, read gauge on GM
compressor outlet.
|
4.0 Routine Maintenance
4.1 G-M Circuit Maintenance
The G-M adsorber must be replaced every 10,000 hours of operation
(Quantum part number MODEL Q-ADSORBER-SC)
|
4.2 Cold-Head Maintenance
When cooling power diminishes after 12,000-17,000 hours of operation,
the model 1020 cold heads will require a maintenance kit overhaul
of seals (Quantum part number Q-1020-KIT).
|
4.3 Compressor Maintenance
In the event of an overtemperature condition they will switch
off and restart after cooling down. In the event of a total pressure
loss they will switch off.
The lubricant is in a closed-loop. In the event of low lubricant
level (which can only occur in the event of a failure in the lubricant
recovery circuit), they become very noisy as the remaining lubricant
slugs its way through in pulses of a few seconds duration. In this
event, switch the compressor off before damage occurs.
The compressors are not field serviceable. In the event of difficulties,
they must be returned to the factory for service
|
4.5 Decontaminating the JT Loop
In closed-cycle operation, contaminants gradually accumulate
by freezing out at the J-T valve. These may eventually cause the
J-T flow to stop and the system will warm up to the G-M second stage
temperature.
Symptoms are: Third stage temperature (normally 4K) will be
at 15K or above. Second stage temperature below 15K. No flow through
JT loop results in a very low (vacuum pressure of - 0.5 bar = -
15''Hg) on the JT compressor return line.
If the G-M cooler is switched off and the system is allowed
to warm up to room temperature, the contaminants will clear themselves;
the cryocooler may then be restarted and it will operate for some
time before becoming plugged again. However, in this procedure the
contaminants remain trapped in the J-T loop.
Materials required: |
Pure Helium: 99.9999% He 6.0 certified with
neon, 1ppm and individually tested cylinder of helium supplied
through a high purity metal diaphragm 0-300 psi [20 bar] regulator.
|
Equipment Required: |
J-T Charge Services manifold
J-T Vent Services manifold |
|
4.5.1 Minor Contamination of the J-T Loop
After some time (especially within 1 day of initial installation
of charges to the system).contaminants may accumulate/freeze in
the J-T loop, reducing the J-T loop flow. Refer to the J-T loop
flow diagram.
This procedure, if not followed correctly may result
in overpressure in the JT loop and destruction of the heat exchanges.
Quantum will not be responsible for damages caused by overpressures.
- Before starting: Ensure that two relief manifolds P7 and
P8 are still installed on top of the liquefier.
BACKFLUSH METHOD:
(a) While the system is cold, switch off the JT compressor.
Before disconnecting Aeroquips ensure that JT return pressure
is above atmospheric. The valve on the buffer tank should be
fully opened to allow pressure equalisation;
(b) After JT return pressure has equalised disconnect the
JT supply and return lines going to the JT compressor.
(c) Switch off the G-M compressor;
(d) Connect the service manifold P20 to the JT supply sides
at the end of the hose, which was disconnected from the cross
P5. Using a hexagonal Allen wrench the relief valve R100 pressure
setting should be reduced to 50 psi;
(e) Allow the system to warm to room temperature (the J-T
loop will vent through the relief valve R100);
(f) Connect pure helium gas to the JT return at the end
of the hose which was disconnected from the compressor;
(g) Open V102 and allow it to vent down to 15 psig (1 bar),
then quickly close V102;
(h) Pressurise the JT loop to 240 psig (8 bar). Then close
valve;
(i) Repeat (f) and (g) a total of 40 times;
(j) Remove the service manifolds and reconnect the lines
to the compressor and restart the system.
|
4.5.2 Major Contamination of the J-T Loop
In some circumstances (major leaks, component failure etc.),
the JT loop may become exposed to air. This large quantity of air
must be removed with the following procedures. Perform the following
steps with the liquefier OFF and WARM.
(a) Turn all compressors, JT's and GM OFF. Wait for liquefier
to warm to room temperature;
(b) Connect the system as shown in the diagram "GM/JT
Interconnections";
(c) Connect the pure helium supply to V103;
(d) Carefully purge the regulator and connecting line;
(e) Bleed down the JT loop SLOWLY to 5psi through V102
(NOTE: This should take about 1 hour). Excessive speed may cause
the lubricant to migrate out of the compressor and seriously
contaminate the JT loop;
(f) SLOWLY (1 hour) repressurize the JT loop, through V103,
to the normal charge pressure as listed in section 3.3. Then
operate the JT loop for 15 minutes with the bypass valve fully
open;
(g) Repeat (e) and (f) two times and
(h) The system may be operated with the service manifolds
in place or removed as desired. Normal practice is to remove
the manifolds so as to reduce the risk of leakage.
|
4.6 Purification of GM compressor
NOTE: The JT circuit requires higher purity than the normal
operating purity of the GM circuit. Consequently, it is necessary
to clean the GM circuit and GM coldhead prior to connecting to the
JT circuit.
1 With GM compressor connected to GM coldhead only, operate
coldhead for at least 4 hours. This allows the impurities (water
& air) to freeze in the GM coldhead.
2 While it's still cold, turn off compressor and immediately
disconnect GM return and GM supply lines from the coldhead
NOTE: This keeps the contamination in the coldhead. The compressor,
lines and adsorber are all clean now.
3 Connect vent Aeroquip adapter to GM return on the coldhead
to depressurize the coldhead.
4 Allow the coldhead to warm up to room temperature.
5 Connect a supply of pure Helium gas at 150 psi to the
GM supply fitting of the coldhead.
6 Disconnect the vent line from the Gm return.
7 Run the coldhead electrical without any helium flow through
it for five minutes.
8 While coldhead still running, alternately pressurised
the coldhead to 150 psi and then depressurise, always pressuring
through the GM supply line and depressurising through the GM
return line.
9 Repeat 7 & 8 five times for a total of 25 charges.
10 With the coldhead pressurised, disconnect the lines.
It is now clean and ready to use.
This long purging sequence is necessary to remove the
water from the coldhead.
|
5 Non-Scheduled Maintenance
Non-scheduled maintenance may be required in the event of a
component failure or of exposure of any part of the extremely high
purity helium system to the atmosphere.
Special procedures, tools and equipment are necessary for non-scheduled
maintenance. Contact Quantum Technology Corp. for further information
before proceeding.
Quantum Technology Corp. Quantum Technology Corp.
1370 Alpha Lake Road, Unit #15 250 H Street, PO Box 8110-183
Whistler, B.C. Blaine, WA
Canada, VON 1B1 USA, 98230
Phone: (604) 938-0030 Phone: (360) 647-9211
Fax: (604) 938-0061 Fax: (360) 671-2955
e-mail: quantum@whistler.net
|
5.1 Re-evacuating the Vacuum Dewar
Occasional pumping on the vacuum dewar may be required to compensate
for outgassing of the superinsulation. If the superinsulation is
ever exposed to helium gas, it will be necessary to pump for 24
hours to remove the helium.
(a) Warm the dewar to room temperature.
(b) Connect a clean vacuum pumping line to the closer dewar
vacuum valve and to a good vacuum pump with liquid nitrogen
trap capable of reaching less than 0.1 microns of Hg pressure.
(c) Evacuate the connecting line and ensure that it does
not leak by checking the pump's vacuum gauge.
(d) Fully open the vacuum pumping valve.
(e) Pump until the vacuum dewar reads 100u or less.
(f) Close the valve and cap the port.
If the pressure reads less than 100 microns at room temperature,
it is normally not necessary to use a vacuum pump as the liquefier
will cryopump itself as it cools (unless the residual gas is helium).
|
6 System Interconnections
The system interconnections are shown in the following figure.
- GM/JT Interconnections
|
|
7 Dewar Schematic and Temperature
Sensor Positions
7.1 Sensor Calibration Data
|
8 Operating Log Sheets
|
9 Operational Test Results
|
9.1 Cooldown Results |
9.2 Cooling Power Results
Appendix A |
System Labels |
Appendix B |
Packing List |
Appendix C |
CTI Cold Head Manual |
Appendix D |
J20 Compressor Information |
Appendix E |
Drawings |
|
10 Quantum Cooler J-20 Compressor
The Quantum Cooler J20 is a highly reliable, single stage, water
cooled, oil lubricated scroll compressor. The refrigerant is gaseous
Helium.
The compressor is maintenance free.
Cooling water of sufficient flow and temperature is required
to circulate through the compressor to prevent overheating. The
definitive parameter is that the cooling water at the outlet of
the compressor should not exceed 30 C. The flow thus depends on
the inlet temperature. For a typical input temperature of 10 C with
a typical heat load of 4kW, the minimum flow of water at 10C is
4000W/((30C-10C)* 4.19J/grC) = 50gr/sec = 3L/m. To achieve this
flow requires a nominal pressure difference of 20PSI or about 1
BAR.
In the event of over temperature the compressor will switch
off and restart after cooling down.
In the event of a Helium pressure loss it will shut down at
30PSI outlet pressure.
The lubricant is in a closed loop. In the event of a low lubricant
level due to a recovery failure the compressor becomes very noisy.
The level at the sight glass will have also fallen to empty. In
this event switch the compressor off and get in touch with Quantum
Technology Corporation.
The compressor is not field serviceable. In the event of difficulties
is should be returned to the factory for service.
|
Quantum J-20 Compressor Parts Description
P1 |
inlet pressure gauge |
P2 |
outlet pressure gauge |
CV |
check valve |
Compressor |
5KW scroll compressor |
VBYPASS |
forms a loop between compressor outlet and
inlet, used as a dummy load for testing compressors. |
SG1 |
sight glass shows oil leaving compressor.
While compressor is running sight glass should always show a
steady mix of gas & oil rushing by. |
SG2 |
sight glass shows level of oil in buffer tank.
Should always read somewhere between full and empty. |
SG3 |
1st stage oil separator sight glass. May show
very slow flow of gas bubbles and oil travelling upwards. |
SG4 |
2nd stage oil separator sight glass. May show
very slow flow of gas bubbles and oil travelling upwards. |
SG5 |
3rd stage oil separator sight glass. Should
never show flow of gas and oil. |
VT1&VT2 |
bypass valves can be used to change 1st and
2nd stage oil separators. Should always be closed. |
VHe-CHG |
Helium charging port valve |
SG6 |
Oil detector sight glass. Should always by
dry. |
PRV |
375 PSI pressure relief valve |
PS1 |
pressure switch. - |
For GM compressors:
-For JT compressors:
|
off>400PSI
off< 35PSI
off>150PSI
off< 35PSI
|
pressure switches have a noticeable amount of hysterisies. |
T1-T3 |
oil separators |
BUF |
oil buffer tank |
VLUBE-CHG |
oil charge port valve |
CB1 |
10 A circuit breaker |
C1 |
3 phase motor contractor |
T1 |
480V -120V step down transformer |
CB2 |
1 A circuit breaker (push to reset |
SW1 |
SPDT toggle switch. Compressor can be controlled
remotely when switch is open. |
R1 |
24VDC relay, supplying 24VDC to pins 1 and
3 of the 14 pin connector at the rear of the compressor allows
the compressor to be switched on and off remotely. |
|
|
|
11 Closed Cycle Water Cooler
Installation Instructions
1 Remove hose connecting the coolant "in" and
"out" of the green radiator. A small amount of coolant
spillage is normal.
2 Connect a long hose from the compressor "water out"
to the radiator "water in".
3 Connect the other long hose from the compressor "water
in" to the radiator "water out".
4 Pressurise the system (with air) to 20 PSI by way of
the schrader valve on the bottom of the orange diaphram tank.
5 Apply power (220V 50Hz)
6 Since the volume of air trapped in the hoses and compressor
will eventually escape out the air relief vent (above fill valve)
the pressure of the system will drop as the air escapes. It
is necessary to periodically re-pressurise the system to 20
PSI until all of the air has escaped. Provided that the system
is running this should not take longer than a day or two.
|
Operational Instructions
1 Water out of the compressor should not exceed 60 DegC.
Water into the compressor should not exceed 35 DegC.
2 If there is a situation where the ambient temperature
of the location of the radiator exceeds 30 DegC it will not
work. The radiator gives off over 3KW of energy in the form
of heat so make sure this will not be a problem in the location
chosen.
3 If there is a situation where the temperature of the
coolant exceeds the maximum, (aprox. 65DegC) the compressor
will shut down and the high temperature trip has to be manually
reset. (back of compressor)
|
|
|