M2 and Dummy News

June 2007

 

M2 unpacked checked and loaded back into Transport Containers

 

 

 

Telescope News

June 2006

Yoke was successfully installed into the Enclosure.

 

Minor alterations had to make to the enclosure doors

 

All went smoothly without hitch and mated to the bearing without problem!

June 2005


East View of Telescope - Lifting and attachment of Altitude Ring onto Yoke

The altitude was fitted out with bearings, motors and ancillary gear while at ground level after which it was lifted as an assembly and aligned and attached to the azimuth axis yoke.

 


M1 cell lift19 - Lifting and Attachment of M1 cell to Altitude Ring

In the same manner as the Altitude the M1 cell has been partially fitted out at ground level before being lifted as an assembly to be aligned and mounted to the altitude ring.


 

May 2005


the VISTA Altitude Ring or Centre Section after machining and painting at PCC in Pennsylvania, USA


taken through the bore of one of the altitude axles and the matt black coating of the surfaces that will surround the optical beam can clearly be seen


shows one of the altitude bearing housings that support the centre section via two pairs of tapered roller bearings

 


March 2005

Pictures of the yoke now on the azimuth bearing

 

 

 

 

 

 

 


Altitude Ring

November 2004 -Altitude Ring being fabricated at PCC, York USA


28 July 2004 Delivery to VPO of Prototype Axial supports

Axial Actuator with pistonAfter VertexRSI satisfactory completion of testing of the Axial supports, two prototypes including their associated control hardware were delivered to VPO. The delivered equipment will be mainly used in interface testing of the M1 Local Control Unit. Pictured below is one of the two axial actuators incorporating a preloaded piston driven by a Bellofram diaphragm, a contact head assembly with low lateral stiffness and a high accuracy load cell.

 

 

16 June 2004 Final design Review Meeting: Part 2

16 April 2004 Final Design Review Meeting: Part 1

6 November 2003 Successful Completion of Preliminary Design

21 – 24 May 2003 Contractor Visit to VLT Paranal Observatory

29 February 2003 Contract Start

 

 

 

 

 