Feb.01 The BSM is now in the final stages of design and intitial prototypes are being built. Presentation.
Mar.01 An alternate prototype has also been explored to provide backup options in the areas of the higher risk technologies of the baseline design. Presentation.
Mar.01 SPIRE documentation is available on the ESA Livelink site
Apr.01 The BSM has been presented at the SPIRE Intermediate Instrument Review, 23-24.April.01. Presentation.
Jun.01 The latest 3D models of the BSM have been incorporated on the SPIRE structure by MSSL. Images are available 1 2 3 4
Jul.01 Preparation for the DDR scheduled for 30.Jul.01
Aug.01 Design presented at DDR level.A few items to close out but looking good. 2 axis prototype build
Oct.01 Product Assurance plan rolled out. Presentation.
Jan.02 Development Model (DM)released for manufacture
Feb.02 Detailed 2 axis prototype warm testing completed, including control loop tests. Preparation for cryo tests started. Kick-off meeting on random response FEA held. Magnetic modelling underway at MPIA. Representative Zeiss/PACS motors received. This will require a re-design of DM to accomodate (designated DM-2). DM-1 model manufacture in an advanced state. Cryo-upscreen rig design complete and placed with workshop for manufacture. Brazed CuBe pivots (chop axis type) order placed with C-Flex.
Mar.02 Cryostat cold repeatability & linearity tests performed - looks good (though needs to be confirmed with AR coated window). Problem with noise affecting control loop - need screened wires on BSM, which will only be available with DM-2. DM-1 started assembly. Cryo-upscreen rigs manufactured and assembled. Tentative booking for warm vibration tests requested with RAL work on justification/test plan in hand.. IBDR presentation given. Draft SMEC/BSM simulator philosophy for integration and tests discussed
Apr.02 Cryostat warm repeatability & linearity tests performed with AR coated window PTFE coated STP/STT wire for DM-2 sourced from RAL, common procurement of wire for future models discussed with RAL. DM-1 assembled and fastener torque procedure detailed. Warm shake of DM-1 and 1 off flex pivot upscreen rig completed successfully!
May.02 DM-2 in manufacture
Oct.02 Delivery of Structural thermal model. DM-2 in warm tests.
Jan.03 Cold tests (4K) at ATC.
Feb.03 DM-2 and four flex-pivot up-screening rigs successfully passed a cryogenic cold shake at RAL. This is a major milestone in the BSM programme, and a measure that the design analysis and build quality are fully up to space quality standards.