Main Headline Here
The Importance of SCUBA-2
Primary
- To provide a unique wide-field sub-mm imaging capability at 450
and 850 microns
- Up to 1000 times faster at mapping large areas than SCUBA to the same S/N
- Up to 10 times faster at extracting known point-source fluxes
- To address a wide-range of scientific issues including the ORIGINS questions: How galaxies, stars and planets form
- To act as a wide-field "pathfinder" for the new generation of submm interferometers (e.g. SMA and ALMA)
Secondary
- To keep the UK and the JCMT partners at the forefront of submm astronomy
- To improve the scientific productivity of the JCMT (particularly at high frequencies)
- To develop a foundation for UK expertise in superconducting detector arrays and readouts
- To apply SCUBA-2 type technology to other areas of astronomy (e.g. for instruments on ELTs and space telescopes)
Milestones
Major Milestones
- 01/07/99: Project start date
- 26/10/99: Conceptual design review
- 04/05/00: Array architecture down select
- 31/10/01: Optical design PDR
- 24/10/02: Systems analysis PDR
- 20/11/02: Array technology Proof-of-Concept Review
- 15/03/03: Cryostat PDR
- 24/09/03: Data reduction pipeline PDR
- 16/10/03: Multi-channel electronics PDR
- 5-6/05/04: First Cryostat CDR
- 30/06/04: Final Cryostat CDR
- 09/09/04: Prototype 850 sub array to Cardiff
- 20/05/05: Proto-type MCE to Cardiff
- 06/07/05: Proto-type 450 sub-array to Cardiff
- 08/08/05: Delivery of Dilution Refrigerator
- 03/03/05: Array technology CDR (go for science-grade arrays)
- 01/02/05: Start lab integration at UK ATC
- 27/05/05: 1st Instrument Cooldown
- 08/12/05: Cooldown with DR and 1K box
- 14/04/06: Functional Verification (Phase I)
- 21/03/06: Sensitivity evaluation with 450 prototype complete
- 18/10/06: First 850 science-grade to ATC
- 18/10/06: First 450 science-grade to ATC
- 28/11/06: Start formal verification testing
- 18/01/08: Acceptance Test Readiness Review
- 08/02/08: Acceptance Test Complete
- 17/03/08: Delivery to JCMT
- 01/04/08: Commence Installation at JCMT
- 05/06/08: Start of functional Check-out
- 23/06/08: System Integration begins
- 08/08/08: First Light on telescope
- 15/09/08: Science Grade Wafers to Raytheon
- 06/02/09: CE modules ready for first S-G arrays
- 16/02/09: Hybridisation for remaining S-G arrays
- 05/03/09: Cardiff Test for 1st science-grade array
- 26/05/09: New Magnetic shields ready
- 20/07/09: First S-G arrays ready for delivery
- 07/08/09: Post-processing of remaining S-G arrays
- 14/09/09: Re-commission with two S-G arrays
- 23/11/09: Post-processing of remaining S-G arrays
- 11/11/09: On-sky commissioning begins
- 13/01/10: Science Readiness Review
- 15/02/10: S2SRO begins
- 24/03/10: End of SRO and Warm up
- 09/04/10: Remove and ship 2 arrays back to UK
- 29/07/10: Ship 8 arrays to Hawaii
- 09/08/10: Array installation begins at JCMT
- 29/09/10: Re-commission instrument - test arrays
- 29/10/10: Re-commission instrument - on-sky
- 18/11/10: Earliest Start of full science operations
Recent Accomplishments
- Start of proto-type array production in June 2003
- Successful PDR for multi-channel electronics
- Contract for a liquid cryogen-free dilution fridge has been placed with Leiden Cryogenics
- Contract for SCUBA-2 mirrors has been placed with TNO/TPD in Holland
- Successful PDR for pipeline processing software
- Contracts for Vacuum Vessel and 4K Structure have been placed with NTE (Poole)
- Cost and Management Review completed October 2004
- Demonstration of 2-D multiplexing on the proto-type sub-array
- Completion of the 60K radiation shield detailing
- Delivery of the final cold mirror
- Release of the warm mirror drawings for manufacture
- Final version of the DR software requirements document released
- Release of Alex's report on sky removal
- Funding for full term of instrument confirmed
- Delivery of the prototype MCE to Cardiff
- Delivery of the 60K radiation shield to the UK ATC
- Completion of warm tests on the cold shutter
- Successful completion of the bump bonding for the 450 prototype
- High quality 450 science-grade detector wafers in hand
- Continued good progress on data reduction/pipeline software
- Tenders issued for instrument mounting frame and tertiary mirror module
- CoDR report issued for the telescope infrastructure work
- Start of instrument assembly and integration
- Prototype Multi-channel Electronics (MCE) delivered to Cardiff
- First instrument cooldown
- Delivery of dilution refrigerator
- 450 prototype array to Cardiff
- Successful operation of the DR and pre-cool system in test cryostat
- Integration of 1K box, focal plane units and DR into the main SCUBA-2 cryostat
- Delivery of all warm mirrors to JAC
- All production MCE modules (except power supply) in manufacture or test.
- Successful demonstration of filtering and flux-jumping firmware
- New FFT processing algorithm selected to enable real-time Quick-Look analysis of FTS data.
- Cooldown#4 with first array installed in the maininstrument
- New, in-house bonding jig UoE likely to improve quality of future detector wafers
- Good progress on MCE hardware production and testing
- Demonstration of Quick-Look for scan map observing mode
- Internal design review for polarimeter revealed no major issues
- Preliminary version of FTS pipeline released
- Functional verification
- Cooldown #5 and #6
- First 850 and 450 Science grade to UK ATC
- Completed formal verification testing
- Acceptance tests completed
- Provisional acceptance for delivery to JCMT
- Initial deep etch trials have shown that the level of pixel undercut can be minimised
- Heriot Wat University have demonstrated a laser dicing capability for future arrays
- FTS measurements have confirmed the central frequency and bandpass for 850um filter
- SCUBA-2 has arrived in Hilo10 March 2008
- Successful FDR held for the Polarimeter
- Commissioning grade arrays have arrived at JAC
- MUX wafers for the science-grade array batch are close to completion
- Completion and issue of report on the redesign of the cold electronics module
- Succesful test of the data reduction pipeline using data from a simulated observing run
- Completion of MUX wafer screening with potentially all wafers being science grade
- cooldown of the instrument to base temperature
- Final alignment checks of entire warm optical system
- Good progress in integrating SCUBA-2 into the observing system
- Successful Integration of the Survey Definition Tool with the JCMT OT
- Achieved 1st light status on the JCMT on 8 August 2008
- Science-grade wafers to Raytheon 12 September 2008
- Test Programme Review 25 September 2008
- Re-commence instrument testing 20 October 2008
- Testing of new CE module at Cardiff
- Good results from the tests of the newcold electronics module
- successful demonstration of a SQUID-2 servo in engineering software to compensate for the magnetic pick-up
- Completion of the hybridisation of the first two S-G arrays
- New magnetic shields ready
- Cardiff tests completed on 450 S-G array
- Sucessful completion of the instrument testing with two new arrays
- start of the on-sky commissioning
- delivery of the 6 remaining arrays to the UK for post-processing
- First interferograms with the FTS during laboratory tests prior to ARR
- Successful Science Readiness Review with the go-ahead for S2SRO
- Re-orientation of the C2 to resolve the trefoil aberration issue
- Thermal conductance of the new CEM wire is close to modelled value
- Identification of new observing strategies to possibly improve data quality
- completionof the deep etch work on all 6 remaining arrays
- Acceptance of the FTS and the polarimeter for delivery
Near Term Goals
- Start Science Operations on JCMT by November 2010